Question: Following are the three estimates for a project: Task Predecessor(s) Duration (days) Optimistic Most Likely Pessimistic B None 10 9 10 10.75 O B 7
Following are the three estimates for a project:
| Task | Predecessor(s) | Duration (days) | Optimistic | Most Likely | Pessimistic |
| B | None | 10 | 9 | 10 | 10.75 |
| O | B | 7 | 6 | 7 | 8.2 |
| L | B | 4 | 3.8 | 4 | 4.2 |
| D | O, L | 8 | 7.5 | 8 | 8.9 |
| | | | | | |
Calculate the completion time variance for Task A.
0.274
0.004
0.085
0.054