Question: Given the time-phased work packages and network, complete the baseline budget form for the project. 0 1 O Design prototype 0 2 2 2 O
Given the time-phased work packages and network, complete the baseline budget form for the project.


0 1 O Design prototype 0 2 2 2 O Build prototype 2 5 5 5 3 Order parts 8 2 4 5 9 1 Prepare production 6 10 4 10 5 5 10 O Prepare marketing 5 10 5 10 6 12 0 Assemble & test 10 2 12 ES SL LS 12 ID 12 O Launch Description DUR 7 EF 1 LF 13 13 Cost by week ($000) - This part is provided for your reference Design prototype Build prototype Order parts Prepare production Prepare marketing Assemble & test Launch Design prototype Build prototype Order parts Prepare production 2956692 295969 Prepare marketing Assemble & test Launch Total Cumulative 12 10 16 18 12 2. Complete the baseline budget form below. Time-phased budget ($000) Budget 24 30 10 64 30 12 36 12 206 10 10 18 0-1 10 22 0 1-2 16 6 12 2-3 3-4 4-5 5-6 6-7 7-8 2 9-10 10-11 11-12 12-13
Step by Step Solution
3.46 Rating (149 Votes )
There are 3 Steps involved in it
To complete the baseline budget form we need to distribute the budget across the given time phases a... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (2 attachments)
6094eabb48423_25362.pdf
180 KBs PDF File
6094eabb48423_25362.docx
120 KBs Word File