Two runs of Risk Analysis were executed for a project using @Risk software. The first run used
Fantastic news! We've Found the answer you've been seeking!
Question:
Two runs of Risk Analysis were executed for a project using @Risk software. The first run used most likely durations for each activity in the “duration” column. The second run used mean durations for each activity in the “duration” column. Most likely durations for each activity are higher than their means. Both runs used 1000 simulations each. The mean duration for the project in the risk output report for the first risk analysis run will be higher than the second run.
True or False