Question: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ are activities for which the earliest start time and the

_______________ are activities for which the earliest start time and the latest start time are equal.
A.
Necessary activities
B.
Important activities
C.
Optional activities
D.
Critical activities