Question: # 1 0 . 1 5 1 0 . 1 5 Consider a project with the following information. Construct the project activity network using AOA

#10.15
10.15 Consider a project with the following information. Construct the project activity network using AOA methodology and label each node and arrow appropriately. Identify all dummy activities required to complete the network.
\table[[Activity,Duration,Predecessors],[A,3,-],[B,5,A],[C,7,A],[D,3,B, C],[E,5,B],[F,4,D],[G,2,C],[H,5,E, F, G]]
\table[[Activity,Duration,ES,EF,LS,LF,Slack],[A,3,0,3,0,3,-],[B,5,3,8,5,10,2],[C,7,3,10,3,10,-],[D,3,10,13,10,13,-],[E,5,8,13,12,17,4],[F,4,13,17,13,17,-],[G,2,10,12,15,17,5],[H,5,17,22,17,22,-]]
 #10.15 10.15 Consider a project with the following information. Construct the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!