Question: 1 0 . 1 9 When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities

10.19 When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities on the critical path are highlighted with an asterisk: \table[[,Normal,,Crashed],[Activity,Cost,Duration,,Extra Cost,Duration],[ A , $5,000,4 weeks, $4,000,3 weeks 4060,],[A,10,000,5 weeks,,3,000,4 weeks 3660],[ C ,3,500,2 weeks,,3,500,1 week 3500]]