Question: When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are

 When deciding on whether or not to crash project activities, a
project manager was faced with the following information. Activities of the critical

When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk (2+2+4+2+4=14M) a) Identify the sequencing of the activities to be crashed in the first four steps. Which of the critica activities should be crashed first? Why? a) Identify the sequencing of the activities to be crashed in the first four steps. Which of the critical activities should be crashed first? Why? b) What is the project's critical path? After four iterations involving crashing project activities, what has the critical path shrunk to? c) Suppose project overhead costs accrued at a fixed rate of $500 per week. Chart the decl ine in direct costs over the project life relative to the increase in overhead expenses. d) Assume that a project penalty clause kicks in after 19 weeks. The penalty charged is $5,000 per week after 19 weeks. What does the total project cost curve look like when the penalty charges are added? Develop a table listing the costs accruing on a per-week basis. e) If there were no penalty payments accruing to the project, would it make sense to crash any project activities? Show your work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!