Question: When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are

 When deciding on whether or not to crash project activities, a

When deciding on whether or not to crash project activities, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk: (2+2+4+2+4=14M) a) Identify the sequencing of the activities to be crashed in the first four steps. Which of the critical activities should be crashed first? Why? b) What is the project's eritical path? Ailer four iterations involving crashing project activities, what has the critical path shrunk to