Question: 1 . 1 Using the PERT formula, calculate the time ( t ) and variance for all activities.T ime in days Activity Predecessor Optimistic (
Using the PERT formula, calculate the time t and variance for all activities.T ime in days
Activity Predecessor Optimistic a Most likely
m Pessimistic b
A
B A
C A
D A
E B
F C;D
G E
H E
I F;H
J G;H
K I;J
Step by Step Solution