Question: 1 10d Sd 200 60 1 2 2 Questive 1 (15 marka) ID Task name Duration Predecessors Obtain Authorization 2 Hire Analyst 150 3 Plan
1 10d Sd 200 60 1 2 2 Questive 1 (15 marka) ID Task name Duration Predecessors Obtain Authorization 2 Hire Analyst 150 3 Plan training 4 Arrange Logistics 5 Announce training Lining the information in the table above draw a Cunit cuart and PERT chart of the project to determine the earliest completion time for his project and identify the critical path for the project. You must submit: 2) GANTT chart b) PERT chart c) Earliest Completion Time of the project d) Cntical Path Note: Please finish the PERT churt using the format as below Taikams ID: Start day Find de Dur