Question: 1 2 0 k V to 2 3 0 , and it is recommended that this 1 4 0 - mile Addison - Smithfield -

120kV to 230, and it is recommended that this 140-mile Addison-Smithfield-Mesa Valley 345
kV be contracted to some competent engineering firm.
We had sessions with each of the three below mentioned engineering firms to acquaint them
with our needs and learn of their capabilities. The work they will perform is as follows: Make
routine sections; make subsurface investigations; make electrical hardware and general project
designs; and furnish miscellaneous specifications, drawings, and technical data required to
procure the right of way, hardware, structural steel, and the awarding of contracts for
construction. It is estimated this work will total 12,300 labor-hours. There will also be
approximately $144,000 worth of computer
services and general out-of-pocket expenses in addition to the labor-hours.
Bid comparison is:
It is recommended that this contract be awarded to Pettigrew even though their cost per hour is
higher than the others. Total cost will be influenced by the capabilities and productivity of the
company chosen, and, therefore, Pettigrew may not cost us any more; it is the desire of Moren
management to have Pettigrew perform such a job with Moren as our first experience with them.
Both T&B and CE have done considerable work for Moren.
Question
If you were in the position of Mr. Carter, which action would you take on the design engineering
contract?
 120kV to 230, and it is recommended that this 140-mile Addison-Smithfield-Mesa

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!