Question: (1) (25%) The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2,

(1) (25%) The network below represents a project

(1) (25%) The network below represents a project being analyzed by Critical Path Methods. Activity durations are A=5, B=2, C=12, D=3, E=5, F=1, G=7, H=2, I=10, and J-6. E 00 B H H A A G Start 12 D 1 10 1 a. What is the duration of path A-B-G-I-J? b. What is the critical path of this network? c. What is the length of the critical path? d. What is slack time at activity G? e. What is the Late Finish of activity H? (2) (25%) Draw the Gantt chart of ES-EF

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!