Question: 1. [35 Points] [Exercise 5.1] For the project data in Table 5.2, redefine the activity durations in terms of the PERT estimates presented as
![1. [35 Points] [Exercise 5.1] For the project data in Table 5.2,](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/02/65c3c6d4d8537_23665c3c6d4b6d93.jpg)
1. [35 Points] [Exercise 5.1] For the project data in Table 5.2, redefine the activity durations in terms of the PERT estimates presented as follows. Activity A B If the other activity data are the same as presented in Table 5.2, compute the scaled CAF for each activity in the project and use the CAF criterion to schedule the project. Compare the CAF schedule to the ACTIM schedule. TABLE 5.2: PERT Project Data with Resource Requirements 21 = 10 D E F G Predecessor ||||
Step by Step Solution
There are 3 Steps involved in it
Heres the Gantt chart for the project activities based on the redefined PERT estim... View full answer
Get step-by-step solutions from verified subject matter experts
