Question: 1 5 1 point is a project performance measurement technique that integrates scope, schdule, and cost data. Forecasting Integrated change control Flowcharting Earned value management
point is a project performance measurement technique that integrates scope, schdule, and cost data.
Forecasting
Integrated change control
Flowcharting
Earned value management