Question: 1 5 . Here is a network with the activity times shown in days: a . Find the critical path. b . The following table
Here is a network with the activity times shown in days:
a Find the critical path.
b The following table shows the normal times and the crash times,
along with the associated costs for each activity.
Activity Normal Time Crash Time Normal Cost Crash Cost
A $ $
B
C
D
E
F
G
If the project is to be shortened by four days, show which activities, in
order of reduction, would be shortened and the resulting cost.