(15) How does a Gantt chart indicate that two activities will be conducted concurrently (at the same time)?
The boxes for each will be shown side by side with a connecting line.
The horizontal bars for each will occupy the same columns (days).
The boxes for each will come out of two opposite comers of a diamond.
The vertical bars for each will occupy the same rows (days).