Question: 14. How does a Gantt chart indicate that two activities will be conducted concurrently (at the same time)? The boxes for each will be shown

14. How does a Gantt chart indicate that two activities will be conducted concurrently (at the same time)?

The boxes for each will be shown side by side with a connecting line.

The horizontal bars for each will occupy the same columns (days).

The boxes for each will come out of two opposite corners of a diamond.

The vertical bars for each will occupy the same rows (days).

17. Of the following descriptions, which one accurately applies to slack?

time when one project activity is waiting for another activity

time when a critical path is established for a project

time when certain interdependencies are eliminated

time when two project activities conclude at the same time

19. What is the goal of a project portfolio manager?

ensure that clients agree to project terms

ensure that their firm accepts only the right projects

ensure that clients understand project costs

ensure that the project is completed correctly

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!