Question: 14. How does a Gantt chart indicate that two activities will be conducted concurrently (at the same time)? T he boxes for each will be
14. How does a Gantt chart indicate that two activities will be conducted concurrently (at the same time)? T
he boxes for each will be shown side by side with a connecting line.
The horizontal bars for each will occupy the same columns (days).
The boxes for each will come out of two opposite corners of a diamond.
The vertical bars for each will occupy the same rows (days).
17. Of the following descriptions, which one accurately applies to slack?
time when one project activity is waiting for another activity
time when a critical path is established for a project
time when certain interdependencies are eliminated
time when two project activities conclude at the same time
19. What is the goal of a project portfolio manager?
ensure that clients agree to project terms
ensure that their firm accepts only the right projects
ensure that clients understand project costs
ensure that the project is completed correctly
21. What is a downfall to just-in-time manufacturing and inventory management?
Just-in-in time manufacturing and inventory management leads to labor surpluses.
When supply chain disruptions occur, a lack of sufficient inventory on hand can lead to widespread shortages.
Just-in-time manufacturing and inventory management can end up costing companies more money.
When supply chain disruptions occur, retail outlets are left with excess inventory that consumers do not need
22. For strategic planning, managers should choose an aggressive strategy if a SWOT analysis reveals that the organization faces weak external ________ and its external opportunities are matched with internal strengths.
opportunities
threats
strengths
weaknesses