Question: [ 1 5 points ] A small assembly line for the assembly of power steering pumps needs to be balanced. The cycle time is determined

[15 points] A small assembly line for the assembly of power steering pumps needs to be balanced. The cycle time is determined to be 1.5 minutes. Figure below shows the precedence diagram. The task times (in minutes) are shown below for each task.
Using Longest (largest) task time first rule, balance the assembly line.
 [15 points] A small assembly line for the assembly of power