Question: ( 1 5 points ) There are 1 1 assembly tasks for a product. The task times and predecessor relationships are given in the following
points There are assembly tasks for a product. The task times and predecessor relationships are given in the following table.
tableTaskABCDEFGHI,JKTask Time secImmediate PredecessorsAAAB CDEFE HHG I, J
Suppose that the company wants to assemble units every one hour.
Draw the precedence diagram of the tasks, and then determine the assignment of the tasks to the first two workstations using the Ranked Positional Weight method In case of ties, give the priority to the task with the highest positional weight