Question: ( 1 5 points ) There are 1 1 assembly tasks for a product. The task times and predecessor relationships are given in the following

(15 points) There are 11 assembly tasks for a product. The task times and predecessor relationships are given in the following table.
\table[[Task,A,B,C,D,E,F,G,H,I,J,K],[Task Time (sec.),40,25,31,25,30,34,35,5,15,40,35],[Immediate Predecessor(s),-,A,A,A,B, C,D,E,F,E, H,H,G, I, J]]
Suppose that the company wants to assemble 48 units every one hour.
Draw the precedence diagram of the tasks, and then determine the assignment of the tasks to the first two workstations using the Ranked Positional Weight method (In case of ties, give the priority to the task with the highest positional weight).
 (15 points) There are 11 assembly tasks for a product. The

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!