Question: 1. [5 pts) Consider the following project. A START D END B E Activity Duration A B D E 5 2 3 7 1 Compute

1. [5 pts) Consider the following project. A

1. [5 pts) Consider the following project. A START D END B E Activity Duration A B D E 5 2 3 7 1 Compute the earliest start time, the earliest finish time, the latest start time, the latest finish time, and the slack of each activity. Activity Name or Symbol Earliest Start Earliest Finish A ES EF LS LF 2 Latest Start Latest Finish Activity Duration C Slack for C= Slack for A = A 5 START END B Slack for D= 2 Slack for B = :D Slack for E=