Question: 1. (5 pts] Consider the following project. C A START D END AN Activity Duration A 5 B 2 3 D E 1 -NU Arty

1. (5 pts] Consider the following project. C A
1. (5 pts] Consider the following project. C A START D END AN Activity Duration A 5 B 2 3 D E 1 -NU Arty Compute the earliest start time, the earliest finish time, the latest start time, the latest finish time, and the slack of each activity. Slack for Ca Slack for A = START END CD CD Slack for D Slack for B Slack for E