Question: 14. Consider the following project. C A START D END B E Activity | Duration A 5 B 2 3 D 7 E 1 (a)

14. Consider the following project. C A START D
14. Consider the following project. C A START D END B E Activity | Duration A 5 B 2 3 D 7 E 1 (a) 2 PTS List all possible patlus from the start node to the end node, and compute the duration of each path Path Duration (b) (2 PTS) Determine the critical path ((21) Compute the duration of the project