Question: 1 6 0 0 0 4 1 1 Given the project information in the following table, what is the probability of completing the project in

16
000411
Given the project information in the following table, what is the probability of completing the project in 70 days?
\table[[Activity,Predecessor,Optimistic (a),Mosk Likely (m),Pessimistic (b)],[A,None,17,29,47],[B,A,6,12,24],[C,A,16,19,28],[D,B,13,16,19],[E,C,2,5,14],[F,D,E,2,5,8]]
 16 000411 Given the project information in the following table, what