Question: 1 7 0 Chapter 4 - Planning Projects, Part 1 1 0 . is a time - phased budget that project managers use to measure

170
Chapter 4- Planning Projects, Part 1
10. is a time-phased budget that project managers use to measure and monitor cost performance.
A. cost baseline
B. cost estimate
C. life-cycle budget
D. cash flow analysis