Question: 1 7 . For the network shown: a . Determine the critical path and the early completion time in weeks for the project b .

17. For the network shown: a. Determine the critical path and the early completion time in weeks for the project b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule. Activity Normal Time Normal Cost Crash Time Crash Cost A 5 $7,0003 $13,000 B 10 $12,0007 $18,000 C 8 $5,0007 $7,000 D 6 $4,0006 $5,000 E 7 $3,0006 $6,000 F 4 $6,0003 $7,000 G 4 $7,0003 $9,000 PLEASE SHOW ALL WORKING AND HOW THE SOLUTION WAS OBTAINEDThe following table represents a plan for a project:
a. Construct the appropriate network diagram.
b. Indicate the critical path.
c. What is the expected completion time for the project?
d. You can accomplish any one of the following at an additional cost of $1,500 :
(1) Reduce job 5 by two days.
(2) Reduce job 3 by two days.
(3) Reduce job 7 by two days.
If you will save $1,000 for each day that the earliest completion time is
reduced, which action, if any, would you choose?
e. What is the probability that the project will take less than 30 days to complete?
 17. For the network shown: a. Determine the critical path and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!