Question: 17. For the network shown: a. Determine the critical path and the early completion time in weeks for the project b. For the data shown,

17. For the network shown:17. For the network shown: a. Determine the

a. Determine the critical path and the early completion time in weeks for the project

b. For the data shown, reduce the project completion time by three weeks. Assume a linear cost per week shortened, and show, step by step, how you arrived at your schedule.

Activity

Normal Time

Normal Cost

Crash Time

Crash Cost

A

5

$7,000

3

$13,000

B

10

$12,000

7

$18,000

C

8

$5,000

7

$7,000

D

6

$4,000

6

$5,000

E

7

$3,000

6

$6,000

F

4

$6,000

3

$7,000

G

4

$7,000

3

$9,000

PLEASE SHOW ALL WORKING AND HOW THE SOLUTION WAS OBTAINED

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!