Question: 1 9 . 2 A computer - system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.

19.2 A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
\table[[Activity,Immediate Predecessor,Activity Time],[A,-,6],[B,-,3],[C,A,2],[D,B, C,3],[E,C, D,6],[F,E,3],[G,B,9],[H,F, G,3]]
a. Draw the network for this project.
b. Identify the critical path(s).
c. What is the project completion time?