Question: 1 9 . 2 A computer - system installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
A computersystem installation project consists of eight activities. The immediate predecessors and activity times in weeks are shown below.
tableActivityImmediate Predecessor,Activity TimeABCADB CEC DFEGBHF G
a Draw the network for this project.
b Identify the critical paths
c What is the project completion time?