Question: .) a computer system installation project consists of eight activities the immediate predecessors and activity times in two weeks are as follows a 6, b3,
.) a computer system installation project consists of eight activities the immediate predecessors and activity times in two weeks are as follows a 6, b3, c 3 , d 3 , e6 , f 3, g 9, h 3. Draw the network for this project Wat are the critical path activities what is the project completion time