Question: 1 . A computer - system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows: Activity Immediate

1. A computer-system installation project consists of eight activities. The immediate predecessors and activity times in weeks are as follows:
Activity
Immediate Predecessor
Activity Time
A
-------
3
B
-------
6
C
A
2
D
B,C
5
E
D
4
F
E
3
G
B,C
9
H
F,G
As a project manager, where would you focus your attention given your analysis?