Question: 1. A Contracting Officer should consider various source documents such as: SOO/SOW/PWS, synopsis, RFP, exchanges with industry, market surveys, RFIs, etc., to determine if a
1. A Contracting Officer should consider various source documents such as: SOO/SOW/PWS, synopsis, RFP, exchanges with industry, market surveys, RFIs, etc., to determine if a change is in-scope.
True or False
2. This is a change to a solicitation done in the pre-award phase of acquisition:
a. Amendment
b. Modification
c. Supplemental Agreement
d. Equitable Adjustment
3. This is change to a contract done in the post-award phase of acquisition:
a. Modification
b. Amendment
c. Protest
d. Claim
4. If a Constructive Change occurs, the Government may:
a. All of these conditions are corrrect
b. Confirm and fund the change
c. Countermand the change
d. Notify the Contractor that no change is considered to have occurred