Question: 1. (a) Identify the bottleneck activity on this operation process chart. (b) What is the cycle time for the bottleneck activity? (c) Calculate the number
1. (a) Identify the bottleneck activity on this operation process chart.(b) What is the cycle time for the bottleneck activity? (c) Calculate the number of teakettles that can be produced in an 8 hour shift (400 min.), assuming that one worker is assigned to handle each production activity (including operation, inspection and assembly).(d) Explain why this is not an efficient way (i.e., one worker per operation) to produce teakettles.
2. Assume that the activities on each vertical line may be combined to improve the production line efficiency and the bottleneck activity is still assigned with one worker.(a) Based on the bottleneck stations cycle time obtain in Problem 1(b) above, find the minimum number of workers needed to produce the teakettles required in Problem 1(c) above.(b) Describe each workers duties based on his/her new task assignment. Also, calculate the cycle time for each operator. For example
Operator 1: Operations 10 and 20. Cycle time: 1.32 min.
Operator 2: Operation 30 and Inspection 40. Cycle time: 0.33 min.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock