Question: 1) A maintenance project was broken down into a set of seven activities as given below. a. Maintenance Project Activities Activity Preceding Expected Duration activities

1) A maintenance project was broken down into a
1) A maintenance project was broken down into a set of seven activities as given below. a. Maintenance Project Activities Activity Preceding Expected Duration activities (days) K 15 L K 12 M K 2 N LM 2 o L 6 0 3 S NP 9 a. Prepare a CPM network (5 points) b. Determine the critical path associated with the network. (10 points)