Question: 1- a preliminary schedule lists tasks, called activities, in much greater detail than a baseline schedule. true o false 2- when merging activities, the _
1- a preliminary schedule lists tasks, called activities, in much greater detail than a baseline schedule. true o false
2- when merging activities, the _ is used for the ef date of the successor activity
longest ef date b) shortest ef date C) longest es date d) shortest es date