Question: 1. A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for
1. A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for every step are indicated in the table below.
| Sub - Process | Time (min) | No of resources |
| S1 | 12 | 1 |
| S2 | 8 | 1 |
| S3 | 16 | 1 |
| S4 | 10 | 1 |
a.) Assuming infinite demand, what is the utilization of process S2? (answer in decimals)
b.) If customers arrive at a constant rate of 3 customers per hour, what is the utilization of S3? (answer in decimals)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts