Question: 1. A project has 11 activities: Activity-A to Activity-K. a. Prepare a network diagram and list different chains of activities. Use the following information. The
1. A project has 11 activities: Activity-A to Activity-K. a. Prepare a network diagram and list different chains of activities. Use the following information.

The answer should be a min of 400 words in word format
2. Compute the project duration and identify a critical path. Use the following additional information

The answer should be a min of 400 words in word format
I Activity No: Predecessor A BCDEF GH I JK BBDD CF.GE H.I.J Activity AB BCD Duration 2 33 7 E|F|G|H|I|JK 83 510 463