Question: 1.) A project has 6 activities. The table below displays the expected time (in weeks) and budgeted cost for each activity. Activity Expected Time Cost
1.) A project has 6 activities. The table below displays the expected time (in weeks) and budgeted cost for each activity.
| Activity | Expected Time | Cost | Immediate Predecessor |
| A | 4 | $2,200 | -- |
| B | 2 | $2,200 | -- |
| C | 3 | $1500 | -- |
| D | 8 | $2,400 | A |
| E | 6 | $900 | B |
| F | 3 | $3,000 | C |
For the entire project, what is the budget for Week 2? Use ES times. (omit the dollar sign in answer.)
2.) You have determined the following for a given project:
Expected completion time of the project = 42 weeks
Standard deviation of project completion time = 5
What is the probability of completing the project in more than 48 weeks?
Report your answer as a decimal and take it to four places.