Question: An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity. Activity Expected time (weeks) Budgeted Cost
- An IT project requires 6 activities. The table below displays the expected time and budgeted cost for each activity.
| Activity | Expected time (weeks) | Budgeted Cost | Immediate Predecessors |
| A | 3 | $3,000 | None |
| B | 4 | $6,000 | None |
| C | 2 | $7,000 | A |
| D | 5 | $9,000 | B |
| E | 3 | $3,000 | C |
| F | 6 | $8,000 | B,D |
Develop a budget for the 15 weeks of the project using ES times.