Question: 1. A project has a critical path with a duration of 20 weeks and a standard deviation of 4 weeks. There is a 35% chance

1. A project has a critical path with a duration of 20 weeks and a standard deviation of 4 weeks. There is a 35% chance the project will be completed in X weeks or less. What is X? Select the closest answer.

a. 18.4

b. 15.8

c. 21.6

d. 24.2

e. 19.7

2. Consider the following project. Each activity is independent. There are essentially 6 paths with only 1 activity on each.

Task

Normal

Duration

Minimum

Duration

Crash

Cost

A

B

C

D

E

F

5

6

6

6

5

4

3

3

3

3

3

2

$90

$50

$75

$110

$85

$80

What is the minimum cost to reduce the project by three time periods?

a. $240

b. $250

c. $320

d. $350

e. None of the above answers are correct

3. As Project Manager, it is important to deal with the people issues as well as scheduling. which of the following would NOT require your time and attention?

a. In a functional project structure, possibly negotiating with the departments for the people you need.

b. Intentional delaying of a project as the completion date draws near, by people on the project as their means of resisting change.

c. In a functional structure, resistance of team members to working on tasks outside their area of expertise.

d. In pure project structure, the team member's frustration in dealing with two bosses.

e. Motivating team members, especially in a functional structure.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!