Question: Question 8 A project has a critical path with a duration of 2 0 weeks and a standard deviation of 4 weeks. There is a

Question 8
A project has a critical path with a duration of 20 weeks and a standard deviation of 4 weeks. There is a 35% chance the project will be completed in x weeks or less. What is x? Select the closest answer.
18.4
15.8
21.6
24.2
19.7