Question: 1. A project has been defined to contain the following list of activities along with their required times for completion Activity Time (weeks) Immediate Predecessors

1. A project has been defined to contain the
1. A project has been defined to contain the following list of activities along with their required times for completion Activity Time (weeks) Immediate Predecessors 1. collect requirements 2 2. analyze processes 3 1 3. analyze data 3 2 4. design processes 7 2 5. design data 2 6. design screens 1 3,4 7. design reports 5 4,5 8. program 9. test and document 8 7 7 10. install 8,9 1. Calculate the slack time 2. Draw and show the critical path