Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Duration Activity (days) a. organize layout
1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Duration Activity (days) a. organize layout team 3 b. organize modification team 6 6 4 7 4 c. design personnel jobs d. set machinery in place e. connect utilities f. modify conveyor system g. train personnel h. finishing touches 1. run test lot a) Find ES, EF, LS, LF, and Slack values all activities. b) What is (are) the critical path(s)? c) What is expected project duration? d) If activity A is delayed by 1 day, what is new expected project duration? e) If activity D is delayed by 1 day, what is new expected project duration? 5 4 3 P
Step by Step Solution
There are 3 Steps involved in it
a To find ES Early Start EF Early Finish LS Late Start LF Late Finish and ... View full answer