Question: 1. A project is being analyzed with below activities identified. Activities A and B start on day 0. Activity Duration (days) a. organize layout team
1. A project is being analyzed with below activities identified. Activities A and B start on day 0.
Activity Duration (days) a. organize layout team 3 b. organize modification team 6 c. design personnel jobs 6 d. set machinery in place 4 e. connect utilities 7 f. modify conveyor system 4 g. train personnel 5 h. finishing touches 4 i. run test lot 3
a) Find ES, EF, LS, LF, and Slack values all activities.
b) If activity A is delayed by 1 day, what is new expected project duration? c) If activity D is delayed by 1 day, what is new expected project duration?