Question: 1. A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project
1. A project team member has completed an assigned task on time. After updating the project schedule, which of the following steps should the project manager take next? (Give explanations for the correct and incorrect choices)
A. Send an updated schedule to the CCB
B. Send a project status update to the sponsor
C. Release the team member to the functional manager
D. Notify the team member to begin successor tasks
2. A change request has been submitted to change the construction from cinder block to wood frame. Which of the following should be performed first after the change has been approved by the sponsor? (Give explanations for the correct and incorrect choices)
A. Documentation update and review
B. Quality check
C. Team approval
D. Impact analysis
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts