Question: 1. Activity Activity Slack Predecessor Activity Duration (In weeks) a 2 b a 2 3 d 1 e d 2 f e 3 g d,

1. Activity Activity Slack Predecessor Activity

1. Activity Activity Slack Predecessor Activity Duration (In weeks) a 2 b a 2 3 d 1 e d 2 f e 3 g d, f 4 h g 1 a) Draw an Activity on Node Diagram. Compute the early and Latest starting and finish time. Compute slack times. [1 + 2 = 3 marks) b) Find out the possible paths and the critical path. What are the critical activities? [1 mark] c) If we delay activity a and c' by 3 days, how would it impact the project completion time? [1 mark]