Question: Draw an Activity on Node Diagram. Compute the early and Latest starting and finish time. Compute slack times. [.5 + .75 +.75 +.5 = 2.5

Draw an Activity on Node Diagram. Compute the

Draw an Activity on Node Diagram. Compute the early and Latest starting and finish time. Compute slack times. [.5 + .75 +.75 +.5 = 2.5 marks] b) Find out the possible paths and the critical path. What are the critical activities? [1+ .5+ .5 = 2 mark] c) If we delay activity d and e by 3 weeks, how would it impact the project completion time? [1.5 mark]

Activity Activity Slack Predecessor Activity Duration (In weeks) a 2 b - 3 a 4 d b,c 1 2 f d.e 2 g f 4 h g 1