Question: 1. Activity D can be crashed how many times? 2.What is the minimum completion time for the project after crashing? 3. If Egon has a
1. Activity D can be crashed how many times?
2.What is the minimum completion time for the project after crashing?
3. If Egon has a budget of only 3000 for crashing costs, what is the shortest possible completion time
4. How much wukl it cost Egon to reduce the original total project time by 6 weeks?
5. How much did crashing that last (sixth) week cost Egon?