Question: 1. Activity Preceding activity Activity duration A - 6 B A 3 C B 1 D A, B 2 E C, D 5 F E
1.
| Activity | Preceding activity | Activity duration |
| A | - | 6 |
| B | A | 3 |
| C | B | 1 |
| D | A, B | 2 |
| E | C, D | 5 |
| F | E | 2 |
| G | C, E, F | 6 |
-
Draw an AON diagram based on the activities and their relationships given in the table. (1 mark)
-
Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project. (1 mark)
-
Determine the slack time for each path. (1 mark)
-
Find the critical activities and critical path. (1 mark)
-
Determine the length of the project. (1 mark)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
