Question: 1 - An item on a project network is Design Software Completed. This is best described as a ( n ) A . Event B
An item on a project network is Design Software Completed. This is best described as
an
A Event
B Path
CActivity
D Node
E Milestone
An AON project network uses which of the following basic building blocks?
A Arrows
B Bars
CNodes
D Both A and C are correct
E A B and C are all correct
The forward pass in project network calculations determines the
A Earliest time's activities can begin
B Earliest time's activities can be finished
CDuration of the project
D Both A and B are correct
E A B and C are all correct
Strategy considered to be under purview of senior management is:
A Old school thinking
BA new school of management thought
CNecessary in a company structure
D Beneficial to the Project Manager
EDependent on company goals
The advent of project management has been most profound in
A Automobile manufacturing
BConstruction
CInformation technology
D The US Department of Defense
EFilm making
What is least influential in projects?
a Time
b Materials
c Manpower.
Project Scope Management:
a Define scope and control scope
b Executing scope and verify scope
c Closing process and Create work breakdown structure
d All of the above
e Only A & B
The back pass review of the project will indicate the following:
a The latest start of the task.
b The earliest finish of the task.
c The critical path.
d Only A & C
e All of the above
An activity in a project network can be represented by which of the following?
a Arrow
b Line
c Node
d All of the above
what are the activities included in early site work of a project?
b Road preparation.
cReplanting of vegetation.
d Fence and security.
e HSE.
f All of the above.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock