Question: 1 - An item on a project network is Design Software Completed. This is best described as a ( n ) A . Event B

1-An item on a project network is Design Software Completed. This is best described as
a(n)
A. Event
B. Path
C.Activity
D. Node
E. Milestone
2- An AON project network uses which of the following basic building blocks?
A. Arrows
B. Bars
C.Nodes
D. Both A and C are correct
E. A, B, and C are all correct
3-The forward pass in project network calculations determines the
A. Earliest time's activities can begin
B. Earliest time's activities can be finished
C.Duration of the project
D. Both A and B are correct
E. A, B, and C are all correct
4-Strategy considered to be under purview of senior management is:
A) Old school thinking
B)A new school of management thought
C)Necessary in a company structure
D) Beneficial to the Project Manager
E)Dependent on company goals
5-The advent of project management has been most profound in
A) Automobile manufacturing
B)Construction
C)Information technology
D) The U.S. Department of Defense
E)Film making
6-What is least influential in projects?
a. Time
b. Materials
c. Manpower.
7-Project Scope Management:
a. Define scope and control scope
b. Executing scope and verify scope
c. Closing process and Create work breakdown structure
d. All of the above
e. Only A & B
8-The back pass review of the project will indicate the following:
a. The latest start of the task.
b. The earliest finish of the task.
c. The critical path.
d. Only A & C
e. All of the above
9-An activity in a project network can be represented by which of the following?
a. Arrow
b. Line
c. Node
d. All of the above
10-what are the activities included in early site work of a project?
b) Road preparation.
c)Replanting of vegetation.
d) Fence and security.
e) HSE.
f) All of the above.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!