Question: 1. At a weekly meeting during the project implementation, the project manager Charlie used the following table to inform everyone of the current progress.
1. At a weekly meeting during the project implementation, the project manager Charlie used the following table to inform everyone of the current progress. According to this table, find the current progress of the project. (20 points) Activity Baseline Detailed Design Testing Planned Value $20000 $50000 $30000 Percent Completion 90% 90% 100% Actual Cost $10000 $60000 $40000 2. For a project in progress, the current PV-$2200, EV-$2000, AC-$2500, find the current project's SV and project status & CPI and cost performance. (20 points)
Step by Step Solution
3.44 Rating (160 Votes )
There are 3 Steps involved in it
1 To find the current progress of the project we can use the formula for Earned Value EV EV Planned ... View full answer